ANALISIS PENGGUNAAN ALAT BERAT TERHADAP WAKTU DAN BIAYA (STUDI KASUS : PROYEK JALAN RAYA BABATBOJONEGORO KM 72-73)

  • Intan Mayasari Teknik Unisda Lamongan
  • Santi Ayu Sari Unisda Lamongan
Keywords: Heavy Equipment, Time, Cost

Abstract

Roads are infrastructure built by the government to facilitate regional development so that they become assets that must be managed and function optimally. The transportation infrastructure and facilities system as a basic infrastructure is a prerequisite for the economic movement of the region, where the supporting system and transportation infrastructure drivers play a major role in the efficiency and effectiveness of regional economic activities. The purpose of this study is to determine the time and cost of using heavy equipment used in Babat-Bojonegoro Highway Project KM 72-73 completion on paving work.

This research uses the work capacity analysis method, namely by calculating data to find the working capacity of the heavy equipment used, as a basis for calculating the time and cost required for heavy equipment in the implementation of paving work.

From the analysis of the time required by heavy equipment in paving work with a volume of 3612 tons / m3 is 167,5 hours or 24 days. For the total cost of heavy equipment analyzed in paving work amounting to Rp. 405.486.106.

Downloads

Download data is not yet available.

References

Akbar, F., Yamali, F. R., & Dwiretnani, A. (2021). Analisa Pengunaan dan Produktivitas Alat Berat pada Kegiatan Peningkatan Ruas Jalan Simpang Pauh–Air Hitam Provinsi Jambi. Jurnal Talenta Sipil, Vol.4 No.2, 114-119.
Aoliya, I. (2018). Analisa Produktivitas Alat Berat pada Pembangunan Jalan Ruas Lingkar Pulau Marsela Provinsi Maluku Barat Daya. Jurnal Online Mahasiswa (JOM) Bidang Teknik Sipil, Vol.1 No.1, 1-16.
Indriani, M. N. (2018). Metode-Metode Perhitungan Tebal Perkerasan Lentur Jalan. CV. Social Politic Genius (SIG).
Mayasari, I., & Setiawan, A. (2021). Analisis Percepatan Waktu Dan Biaya Proyek Peningkatan Jalan Menggunakan Metode Time Cost Trade Off dengan Penambahan Jam Kerja dan Jumlah Alat(Studi Kasus: Jalan Betoyo-Dagang Kecamatan Manyar Kabupaten Gresik). DEARSIP : Journal of Architecture and Civil, 1(1), 57-70. https://doi.org/https://doi.org/10.52166/dearsip.v1i1.2528
Kalengkongan, B. B., Arsjad, T. T., & Mangare, J. B. (2020). Analisa Perhitungan Produktivitas Alat Berat Pada Pekerjaan Pematangan Lahan Pembangunan Tower Sutet LikupangPaniki. Jurnal Sipil Statik, Vol.8 No.1, 99-106.
Kaprina, A., Winarto, S., & Purnomo, Y. C. S. (2018). Analisa Produktifitas Alat Berat Pada
Proyek Pembangunan Gedung Fakultas Syariah Dan Ilmu Hukum IAIN
Tulungangung. Jurnal Manajemen Teknologi & Teknik Sipil, Vol.1 No.1, 1-11.
Kulo, E. N., Waani, J. E., & Kaseke, O. H. (2017). Analisa Produktivitas Alat Berat Untuk
Pekerjaan Pembangunan Jalan (Studi Kasus: Proyek Pembangunan Jalan Lingkar SKPD Tahap 2 Lokasi Kecamatan Tutuyan Kabupaten Bolaang Mongondow Timur). Jurnal Sipil Statik Vol.5 No.7.
Murti, U. D. (2016). Analisa Produktivitas Pekerjaan Galian Menggunakan Alat Berat Pada Proyek Pembangunan di Balikpapan. Jurusan Teknik Sipil Politeknik Negeri Balikpapan, 1-10.
Noptrius, N. (2021). Analisa Produktivitas Alat Berat Pada Pekerjaan Timbunan Jalan Seberang Taluk-seberang Benai. Jurnal Perencanaan, Sains, Teknologi, dan Komputer, Vol.4 No.1, 416-431.
Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat. (2016). Analisis Harga Satuan Pekerjaan Bidang Pekerjaan Umum.
Yuni, C. (2015). Analisa Produktivitas Alat Berat Pada Proyek Pembangunan Badan Jalan Tenggarong Loa Kulu Dan Loa Janan. KURV
Published
2023-11-30
How to Cite
Mayasari, I., & Sari, S. (2023). ANALISIS PENGGUNAAN ALAT BERAT TERHADAP WAKTU DAN BIAYA (STUDI KASUS : PROYEK JALAN RAYA BABATBOJONEGORO KM 72-73). DEARSIP : Journal of Architecture and Civil, 3(02), 108-117. https://doi.org/https://doi.org/10.52166/dearsip.v3i02.5214