ANALYSIS OF THE APPLICATION OF TIME MANAGEMENT USING THE CPM METHOD IN THE REHABILITATION WORK PROJECT OF THE DISDIKBUDPORA HALL BUILDING
DOI:
https://doi.org/10.52166/dearsip.v6i01.13009Keywords:
Critical Path Method, time management, critical path, project scheduling, construction projectAbstract
Time management is one of the important factors in the successful implementation of construction projects because it is directly related to time efficiency, cost, and quality of work. In the Semarang Regency Disdikbudpora Hall Rehabilitation Project, the preparation of the implementation schedule is still not optimal due to the determination of the duration of work that has not considered the complexity and relationship between activities properly. This study aims to analyze the application of time management using the Critical Path Method (CPM) method to obtain a more effective project implementation duration and identify activities that are on the critical path. The research method used is a quantitative descriptive method by utilizing primary data in the form of field observations and secondary data in the form of time schedules, weekly reports, work drawings, and Cost Budget Plans (RAB). The analysis was carried out using the CPM method through forward pass, backward pass, and total float to determine the critical trajectory of the project. Data processing is done using Microsoft Excel and network visualization is created using AutoCAD.
The results showed that the normal duration of project completion based on the CPM method is 54 working days, 3 days faster than the existing implementation schedule of 57 calendar days. Activities included in the critical path include preparatory work, certain earthworks and foundations, concrete work, wall pairing, floor and wall coverings, and painting work. Activities on critical lines have a total float value of zero, so delays in the work will affect the overall duration of project completion. Based on the results of the analysis, the application of the Critical Path Method (CPM) has proven to be effective in optimizing project scheduling because it is able to identify critical activities and accelerate project completion time. This method can be used as a reference in controlling the implementation time of construction projects to be more efficient and planned.
Downloads
References
Abrar, H. (2010). Manajemen proyek: Merencanakan, penjadwalan, dan pengendalian proyek. Andi.
Afiya, S. N., & Ardana, S. A. (2023). Analisis penerapan manajemen waktu dengan metode CPM pada proyek pembangunan Perumahan Griya Mahari. Universitas Singaperbangsa Karawang.
Ervianto, W. I. (2005). Manajemen proyek konstruksi (Edisi revisi). Andi.
Fredika, A. (2010). Analisa percepatan pelaksanaan dengan menambah jam kerja optimum pada proyek konstruksi (Studi kasus proyek pembangunan Super Villa Peti Tenget Bandung). Universitas Udayana.
Iwawo, E. R. M. (2016). Penerapan metode CPM pada proyek konstruksi (Studi kasus pembangunan gedung baru kompleks Eben Haezar Manado). Fakultas Teknik Jurusan Sipil Universitas Sam Ratulangi.
Lasmito, L. (2021). Analisa Peneprapan Manajemen Waktu pada Proyek Pembangunan Gedung Kantor dan Pendopo Kecamatan Sarirejo. DEARSIP : Journal of Architecture and Civil, 1(1), 41–44. https://doi.org/10.52166/dearsip.v1i1.2527
Rachman, D. N., & Iswendra. (2018). Analisis penerapan manajemen waktu pada rencana proyek pembangunan Gedung Cobalt dan Linac RSMH Palembang dengan menggunakan metode CPM. Universitas Palembang.
Rodhi, N. N. (2024). PERENCANAAN MANAJEMEN PROYEK DALAM MENINGKATKAN EFEKTIFITAS KINERJA SUMBER DAYA MANUSIA DI BOJONEGORO. DEARSIP : Journal of Architecture and Civil, 4(01), 25–32. https://doi.org/10.52166/dearsip.v4i01.6262
SHOLAHUDDIN, M., & Nur Octavia, Y. (2024). PENERAPAN CRITICAL PATH METHOD (CPM) PADA PROYEK REKONSTRUKSI JALAN UNTUK MENGIDENTIFIKASI KEGIATAN PEKERJAAN JALUR KRITIS. DEARSIP : Journal of Architecture and Civil, 4(02), 72–84. https://doi.org/10.52166/dearsip.v4i02.7822
SHOLAHUDDIN, M., & Wati, D. C. (2023). ANALISA KINERJA BIAYA PADA PROYEK PEMBANGUNAN GEDUNG GELANGGANG PRESTASI FIA UNIVERSITAS BRAWIJAYA MENGGUNAKAN METODE EARNED VALUE CONCEPT. DEARSIP : Journal of Architecture and Civil, 3(02), 87–99. https://doi.org/10.52166/dearsip.v3i02.5164