PRODUCTIVITY AND PROCESS ANALYSIS REINFORCED CONCRETE BEAM WORK ON JIIPE GRESIK MOSQUE-BKMS CONSTRUCTION PROJECT
Abstract
Controlling labor productivity in construction projects has a very important role. For example, labor productivity in the early stages of a project can have a major impact on the accuracy of schedules or plans that have been prepared. This study aims to find out the process of implementing block work in the Mosque Construction Project-BKMS JIIPE Gresik and compare the productivity of labor in the installation of beam reinforcement with productivity standards as stated in the Minister of PUPR Regulation No. 1 of 2022.
Observations were carried out directly in the field by recording the number of workers, the volume of work, and the duration of time (working hours) on the B1 Block work for eight working days, starting at 07.00–11.00 WIB. The break time lasted at 11.00–13.00 WIB, and the work continued until 16.00 WIB. In addition, recording is also carried out at the end of working hours every day to obtain process data and worker productivity values.
The reinforced concrete block work in this project uses conventional methods which include the stages of preparation, measurement, ironing, formwork installation, checking, casting, dismantling of formwork, and treatment (curing) which are all carried out at the project site with the support of certain tools. The results of the observation showed that the average labor productivity (blacksmith) for the installation of B1 beam reinforcement work reached 147,390 kg/OH, while the highest productivity was 210,532 kg/OH and the lowest was 93,986 kg/OH.
The results of calculations based on the Minister of PUPR Regulation No. 1 of 2022 show that the standard productivity for blacksmith labor is 142,857 kg/OH. Based on the results of the analysis, it was found that the average productivity of workers in the field had a value of 1,031 times greater than the standard of the Ministerial Regulation on PUPR.
Downloads
References
Albani Musyafa, S. T. (2018). Produktivitas Tenaga Kerja Pada Pemasangan Penutup Atap Genteng Di Lapangan.
Amelia, P., Ayu, E., & Khaidir, I. (2025). PENERAPAN VALUE ENGINEERING PADA PROYEK KONSTRUKSI LABORATORIUM POLTEKES KEMENKES JAMBI. DEARSIP : Journal of Architecture and Civil, 5(01), 101-107. https://doi.org/https://doi.org/10.52166/dearsip.v5i01.9524
Fahrizal, Y. (2017). Beban Kerja Terhadap Kualitas Tidur Pada Buruh Pabrik Di Pt. Yang Ming International Kota Semarang (Doctoral dissertation, Muhammadiyah University of Semarang).
Honandar, C. C. (2021). Desain Gedung Perkantoran 5 Lantai (Doctoral dissertation, Podomoro University).
Indonesia, S. N. (2017). Baja tulangan beton. SNI, 2052, 3-5.
Lubis, C. A. (2018). Laporan kerja Praktek pada Proyek Pembangunan Gedung The Manhattan Mall and Condominium Medan.
Magribi, M. A. (2020). Analisa Produktivitas Pekerjaan Pemancangan Tiang Pancang Pada Proyek Pembangunan Bank BCA KCU Kota Pekanbaru (Doctoral dissertation, Universitas Islam Riau).
Nasional, B. S. (1989). Pedoman perencanaan pembebanan untuk rumah dan gedung. BSN, Jakarta.
Nugroho, A. W., Hasyim, M. H., & El Unas, S. (2014). Analisa Produktivitas Pekerjaan Pelat Lantai M-Panel, Beton Bertulang, Dan Sni Pekerjaan Pelat Beton Bertulang (Doctoral dissertation, Brawijaya University).
Pramesti, H. R., & Priyanto, B. (2023). Analisa Produktivitas Tenaga Kerja dan Harga Satuan Pekerjaan Pada Pekerjaan Pasangan Dinding Bata Ringan. Journal Of Civil Engineering Building And Transportation, 7(1), 38-45.
Proyek Perumahan Di Kota Pekanbaru. SIKLUS: Jurnal Teknik Sipil, 3(2), 100-106.
Setiawan, A., & Mayasari, I. (2021). Analisis Percepatan Waktu Dan Biaya Proyek Peningkatan Jalan Menggunakan Metode Time Cost Trade Off dengan Penambahan Jam Kerja dan Jumlah Alat(Studi Kasus: Jalan Betoyo-Dagang Kecamatan Manyar Kabupaten Gresik). DEARSIP : Journal of Architecture and Civil, 1(1), 57-70. https://doi.org/https://doi.org/10.52166/dearsip.v1i1.2528
Setiawan, A., Shodiq, M., & Mayasari, I. (2024). METODE PELAKSANAAN PEKERJAAN KONTRUKSI KOLOM DALAM PROYEK PEMBANGUNAN MASJID-BKMS JIIPE GRESIK. DEARSIP : Journal of Architecture and Civil, 4(02), 58-71. https://doi.org/https://doi.org/10.52166/dearsip.v4i02.7857
SHOLAHUDDIN, M., & Nur Octavia, Y. (2024). PENERAPAN CRITICAL PATH METHOD (CPM) PADA PROYEK REKONSTRUKSI JALAN UNTUK MENGIDENTIFIKASI KEGIATAN PEKERJAAN JALUR KRITIS. DEARSIP : Journal of Architecture and Civil, 4(02), 72-84. https://doi.org/https://doi.org/10.52166/dearsip.v4i02.7822
Soumokil, M. D. (2022). Tinjauan Struktur Atas (Kolom Dan Balok) Pembangunan Gedung Gereja Lahairoi Hative Besar. Journal Agregate, 1(1), 98-107.
Umum, K. P., & Rakyat, P. (2013). Pedoman Analisis Harga Satuan Pekerjaan Bidang Pekerjaan Umum. Peraturan Menteri Pekerjaan Umum,(11).
Wignjosoebroto, S. (1995). Ergonomi. Studi Gerak dan Waktu, Edisi Pertama, Guna Widya, Jakarta.
Yanti, G. (2017). Produktivitas Tenaga Kerja Dengan Metode Work Sampling.